Start Date:
10 June 2018
Completion Date:
07 April 2020
Project Duration:
700 Days
Client:
Al Jaber Group
Start Date:
10 June 2018
Completion Date:
07 April 2020
Project Duration:
700 Days
Brief Description
The Project is to deliver a purpose designed premium 2,470 student school to continue to best serve the needs of our Doha community. ACS Doha International School Al Kheesa Campus is proposed to have a total floor area of roughly 27,000m2, delivering education to students from pre-school to pre-university, with an age range of three years old until the age of 18. Approximately floor area 28,000m2.
The ACS Doha Intemational School AI Kheesa Campus will comprise:
Main Building (GF+2) of approx. 22750m2;
Early Childhood
Lower School
High and Middle School
Dining areas
Sports Centre (B+GF +1) of approx. 4600m2;
Substation (GF) of approx. 540m2;